A friend thinks you can answer this question about Lean Operations

Your engineering team takes 4 weeks to ship a feature: 3 days coding, 5 days in code review queue, 4 days in QA queue, 2 days integration testing, 2 weeks waiting for the next release train. Using lean principles, what should you fix FIRST?